You are here: Home / NASA/JPL/ESA - 2019 HyTES Joint European Campaign Status

NASA/JPL/ESA - 2019 HyTES Joint European Campaign Status

2019 HyTES Joint Campaign with NASA, European Space Agency (ESA), King College London, Natural Environment Research Council (NERC), National Centre for Earth Observation (NCEO) aboard a British Antarctic Survey (BAS) aircraft.

Overall Status
DescriptionStatus
Instrument In transit to JPL
Current location UK-USA transit
Aircraft Reconfigured for transit
Data Processing All Quicklooks are complete

 

Status Blog

1 July 2019

Hytes image
Removal of HyTES from BAS aircraft with operating vintage aircrafts in the background

30 June 2019

Final Data acquisition flight - 5 scenes captured View Quicklooks

29 June 2019

Data acquisition flight - 12 scenes captured View Quicklooks

28 June 2019

Data acquisition flight - 19 scenes captured View Quicklooks

27 June 2019

Hytes image
Return to Duxford, UK and ready for airborne science flights

26 June 2019

Down day - Morning calibration was performed

25 June 2019

Data acquisition flight - 4 scenes captured View Quicklooks

24 June 2019

Data acquisition flight - 14 scenes captured View Quicklooks

23 June 2019

Data acquisition flight - 18 scenes captured View Quicklooks

23 June 2019

Hytes image
Ready for another afternoon of airborne science

Hytes image
Ground measurements by Kings College London in foreground

Hytes image
Water measurements by the ground team.

22 June 2019

No flights scheduled because of thunderstorms in the area.

21 June 2019

Down day - The pilot is required not to fly.

20 June 2019

Data acquisition flight - 15 scenes captured View Quicklooks

19 June 2019

Data acquisition flight - 14 scenes captured View Quicklooks

18 June 2019

Second data acquisition flight - 13 scenes captured View Quicklooks

17 June 2019

First data acquisition flight - Four scenes captured View Quicklooks

Hytes image

16 June 2019

Welcome to Italy

Hytes image

15 June 2019

Flight Delay: Severe thunderstorms in France has delayed departure from UK by one day.

14 June 2019

Taxi Checklist performed and plane is ready for flight to Italy

Hytes image

9 June 2019

The HyTES instrument is at equilibrium and two calibrations have been performed with good results

Hytes image

9 June 2019

The HyTES instrument is at equilibrium and two calibrations have been performed with good results

Hytes image

7 June 2019

Modifications were completed on the BAS plane and the HyTES instrument is inside the plane and cooling to the operating temperature

Hytes image

31 May 2019

Cooling at operating temperature

30 May 2019

Instrument started Cooling to operating temperature
JPL Engineers verified onboard survey power is active

Hytes image


Hytes image

27 May 2019

HyTES Arrived in UK

17 May 2019

HyTES Departed JPL